Completix

< 1 min read

Timesheets

By default when a user is invited to join a project, the status is set to OPEN. The resource has the ability to book time against the project via Timesheet. Time against a project is used to calculate Effort.

Entries in the timesheet are used to automatically calculate a resource’s forecast. When a timesheet is approved, the values goes against the Actuals.

 

Timesheet entries are available from project Planned Start date until the latest of “Planned end”, “Scheduled end”, or “Allocation end date”

If you don’t see your project in the Timesheet entries, please ask the project manager to verify if you have been added to the project team and if the projects dates (approved and scheduled) are correct.

Timesheets can be accessed in 2 ways:

The Project Team page​
The Project Team page​

When a weekly timesheet is completed, the user needs to “Submit” for approval.

Timesheets and Approval​

Effort Based Schedule

When the “Effort-based schedule” is activated in the project settings, tasks assigned to a resource (if applicable) will appear in the Timesheet. With this option enabled, either a task or an allocation must be assigned to a resource for time submission. If the option is disabled, the resource can submit time solely against the general project.

Timesheet pre-population and Forecasts

Completix makes it extremely easy and painless for a user to fill in their hours. When a resource is allocated, the timesheet is automatically pre-filled with the “allocated” hours. If necessary, the user can override the value before submitting.

The values in the timesheet function as a forecast and are reflected as such.

When the pre-population option (in project settings) is enabled, any effort assigned to a resource, either via allocation and/or via Scheduled task is evenly pre-populated in the resource’s timesheet based on the value and the timeframe

Pre-population comes with an override warning. Whenever creating or changing an allocation/task that affects the resource’s effort, you will be presented with a selection on how to proceed:

pre-population
  • Do not override: Timesheet entries will not be replaced by newly calculated values. When “Do not override” is chosen, pre-population is disabled. Select this option if you prefer a more hands-on method for managing your forecasts.
  • Override all forecast: The newly calculated values will overwrite any entries within the allocation/task timeframe in the timesheet that have not yet been approved. Approved timesheets will remain unchanged. Choose this option for a fully automated approach to managing your forecasts.
  • Override, but keep manually edited entries: This option functions similarly to the Override setting, except that any manually edited entries made by a resource in their timesheet will not be overwritten.
If you select the option to remember your choice, you won’t be prompted again, and the selection will be applied to all effort changes. To modify this behavior after setting an option as the default, you can always go to “project settings” and reset it as needed.

Timesheet approval

After the timesheet has been submitted by a team member, each project manager receives an approval request for their project.

To review an approval task, the assigned user can go to their My Work section in the main menu and go to the My Approval tab

Timesheets and Approval​

The project manager can either approve or reject. If rejected, the user will have the ability to re-submit the portion that was rejected.

Timesheets and Approval​

Once a timesheet is approved, the effort is calculated and reflected in the various dashboard and team page. 

Timesheet approval - Override

A system administrator or a user with the proper permission, can approve on behalf of the project manager. Go to Site Admin/Approvals to action the request.

Overdue timesheet report

To review the status of any overdue timesheet, you can do so by pulling a report from the Executive Dashboard under the Resources tab.

Changelog

Aug 29, 2024

  • New – Users Calendar. Unified view of all user’s calendar
  • New – Vacation calendar. Visualize your resources’ vacations in a searchable centralized calendar
  • New – Allocation Gantt. A new view that represent resources’ allocation in a Gannt chart
  • New – My Availability. Each user can set their own working time and days off. The availability is fully automated with the schedule, forecast and allocation
  • New – Effort based schedule. You can now assign effort to tasks in the schedule and report them in the Timesheet. Timesheet entries are automatically calculated and pre-populated.
  • New – Task based Timesheet. You can now report time against assigned schedule’s tasks. This functionality is tied to Effort based schedule.
  • New   Each project has a dedicated general chat
  • New –  Timesheet custom entries. Add non-billable hours to the timesheet and visualize reports. For example you can track a resource’s vacation days.
  • New   Added new interactive resources’ effort reports with time/cost views
  • New – Multi-Language support
  • Improved –  Timesheet reports now include “To Date” tally
  • Improved – In the resource view, actuals and forecast are now displayed side-by-side
  • Improved – Vendors logos are now automatically added to the vendor component.
  • Improved – New schedule, forecast and actuals triggers have been added to improve the warning engine
  • Improved – Search functionality now includes RAID items
  • Improved – Gantt charts have a new rounded look and have the resource(s) assigned visible in the bar
  • Improved – Raid. You can now hide all RAID items, while in list view, that are closed with the click of a button.
  • Change – Allocation calculation are no longer tied to the project end, and instead rely on the allocation calendar
  • UI tune-up– All dashboards have bigger graphic counters and a new coloring scheme to clearly separate the budget data from the rest.
  • Fix – Various bug fixes

Jun 7, 2024

  • New – Change Request impacting the schedule are now automatically updating the “Approved end date” of the project and are clearly flagged. 
  • New – Project duration (in days) is now displayed in the overview page and in the status report. 
  • Improved – Schedule and RAID filters have been improved
  • New – Baseline capability has been added to the schedule
  • New – Schedule history is now available. The schedule automatically save itself and provides multipole restore points
  • Improved – New triggers have been added to the warning engine to better support more use cases
  • New – Search is now available across the entire site  and covers multiple items
  • Improved: project search now includes RAID items
  • New: In the Simplified view, we have added the Tasks Kanban view. The Kanban view is now the default one

Apr 20, 2024

  • New – Document search is indexed and fully integrated with external drives (OD. GD. etc).
  • Improved – Schedule and RAID filters have been improved 
  • Improved – Milestones in gantt chart are placed in different level when colliding
  • Improved – CSV exports data improvement
  • Improved – Dashboards columns are also customizable “per user” and can be set directly in the dashboard.
  • Fix – Fixed bugs in schedule and RAID where resources couldn’t be copied via context menu

Mar 16, 2024

  • New – OneDrive Integration (2-way) 
  • New – Google Drive Integration (2-way)
  • New – Schedule Kanban view
  • New – Tracking and Operational initiatives have been simplified and add the ability to migrate to a full project
  • Improved – Document templates can now be organized into folders

Jan 29, 2024

  • Improved – Site Settings’ UI has a new look with explanation and guide
  • New – Portfolio status can now be exported unified 
  • New – Jira Integration (2-way)
  • New– MS Project Integration (2-way)
  • New– Simplified view – Record is committed automatically

Dec 22, 2023

  • New – Introduced a FREE plan
  • New – Introduced a new trigger-based Warning engine
  • New – Added charts for budget’s status
  • New– Added Portfolio Manager role
  • New– Added Portfolio view in My Dash for assigned Portfolio Managers
  • New – Project type can be hidden if not in use
  • Improved – Status reports now export in PDF landscape for better readability

Nov 25, 2023

  • Fix – Bugs and UI tune-ups
  • New – RAID Cards in Kanban mode have an updated look
  • New – Added 5 custom budget fields. You can track your own custom financial targets and display them in the various dashboards and status reports
  • New – Budget templates can now be created by importing directly from MS Excel
  • New– When, in a project, components are hidden, all related options are also hidden
  • New– Added a Resource view for Portfolios

Nov 5, 2023

  • Fix – Bugs and UI tune-ups
  • New – Introduced Operational and Task Tracking as type of initiatives
  • New – Project type tags are now colored differently for a better experience
  • New – Project types are now tracked in the Dashboards
  • New– Added ability to show/hide all details’ components separately in the Overview page 
  • New – Added a “Note” field in vendor expenses.

Oct 5, 2023

  • Fix – Bugs and UI tune-ups
  • New – Introduced Financials lock
  • New – Dashboards: added alert icons for values over the baseline 

Sep 6, 2023

  • Fix – Fixed FY calculation in PM Dashboard
  • New – Introduced a new Trial start Welcome guided setup
  • New – Table’s headers have a new and improved look
  • New – Added option to include/exclude any given project in the overall Budget and/or Financials calculations
  • New – Added option to enable/disable the budget fiscal on a per project basis

Aug 25, 2023

  • Fix – Bugs and UI tune-ups
  • Update – We updated all internal libraries to the latest version 
  • New – Introduced a Simplified project type to be used for task tracking type activities
  • New – Increased the number of components that can be turned off separately
  • New – Tasks can now be added directly from the dashboards
  • New – The Trial plan has been simplified by turning off, by default, all advanced components. All features can be turn back on in the Site settings
  • New – Individual users can now customize their dashboards by show/hide columns of data. Go to “My Account” to customize it.

Aug 10, 2023

  • Fix – Bugs and UI tune-ups
  • New – Grouping of resources in MyTeams
  • New – Pre-built budget “Estimates vs Actuals”
  • New – Status report now has a new widget: Summary bar
  • New – More components can be turned off separately
  • New – New tasks can be added directly from the dashboard

Completix for mobile is not ready yet

We are working hard creating a mobile version that meets your needs